Nuclear power plant construction in north Finland faces delay, increased costs and geopolitical uncertainties

Tensions between Russia and the EU could make financing for the partly Russian-own plant more difficult.

By Thomas Nilsen, The Independent Barents Observer - April 30, 2021
1036
Construction work is in full swing at the site at Pyhäjoki, in northern Finland. (Fennovoima via The Independent Barents Observer)

Costs for a controversial partly Russian-owned nuclear power plant under construction in Northern Finland will be as much as €1 billion more than previously estimated, even as geopolitical concerns could affect its financing, says the company building the plant.

“Further deterioration of political and commercial relations between the EU, the USA and Russia could lead to more sanctions between the parties. Such deteriorated international affairs and sanctions could influence the project’s schedule and financing, in particular,” Fennovoima writes in its updated construction license application to Finnish authorities on Wednesday.

Work on the site in Pyhäjoki, south of Oulu, is in full swing although final permission for the reactor itself at Hanhikivi 1 nuclear power plant is not yet granted.

The original application was delivered in 2015, but as Fennovoima sees “changes in boundary conditions,” an updated application was made. Among other things, the application includes an additional survey on the power plant’s impact on the marine environment and fishery during operation.

Other changes are related to security and preparedness arrangements and design solutions, although, no changes to the key principles of the power plant, Fennovoima underlines.

“The rationale for the project is unchanged, and the scope of it will not be affected by the update. The power plant project will be implemented on the Hanhikivi peninsula in Pyhäjoki, as described in the original application,” Joachim Specht, CEO of Fennovoima, said in a statement.

The reactor to be built is of the 4th generation Russian-design pressure water type VVER-1200 with a capacity of 1200 MW, estimated to supply about 10 percent of Finland’s electricity needs.

Russia’s state-owned nuclear corporation holds a 34 percent stake in the plant. For Moscow, export of civilian nuclear power reactor technology is a source of both commercial revenue and of symbolic pride.

“Putinjoki” painted over the road sign on entering Pyhäjoki municipality. Construction of the partly Russian-owned nuclear power plant is controversial. (Thomas Nilsen / The Independent Barents Observer)

Last week, government officials in the Czech Republic said they were kicking Rosatom out of the play for bidding at a planned new reactor for the Dukovany nuclear power plant. The move came amid the diplomatic turmoil between Prague and Moscow following a 2014 blast in a weapons storage which Czech intelligence blames Russian military spies for being involved.

As with the Czech nuclear power plant, Fennovoima’s Hanhikivi 1 reactor is also planned to receive uranium fuel supplies from Russia.

Start-up in 2029

The updated license application says construction of the plan itself might begin in the summer of 2023, given the building license is granted by the Finnish authorities by the summer of 2022.

Current construction work at the site in Pyhäjoki includes workshops, administrative buildings, and early-stage groundwork.

“Commercial operation of the plant would thus begin in 2029,” the application reads. That is a four-year delay compared with the original plans.

Costs estimates climb significantly, up from €6.5-7 billion to now €7-7.5 billion. Fennovoima writes that this is “mainly due to the five-year delay in obtaining the construction license and, to a lesser extent, changes in the project’s scope of supply.”

The nuclear power plant will be the third in Finland and the northernmost in western Europe.