Bid to pause ConocoPhillips’ Alaska Willow project fails

Initial construction can proceed while legal challenges make their way through the courts, Judge Sharon Gleason ruled.

By Clark Mindock, Reuters - April 4, 2023
382
A screen displays the logo for ConocoPhillips on the floor of the New York Stock Exchange in New York City on April 6, 2022. (Brendan McDermid / Reuters File Photo)

A federal judge on Monday rejected a bid by environmentalists to temporarily suspend the U.S. government’s approval of ConocoPhillips’ multibillion-dollar oil drilling project in Alaska’s Arctic.

U.S. District Judge Sharon Gleason in Anchorage had been asked by environmental groups and an Alaska Native group in two lawsuits filed last month for an order blocking construction on the $7 billion Willow project over concerns it would exacerbate climate change and damage pristine wildlife habitat.

Gleason said an injunction was inappropriate because the groups wouldn’t be irreparably harmed by the construction that ConocoPhillips has scheduled for this month, which includes building roads and a gravel mine.

The judge didn’t address whether the lawsuits appeared likely to succeed at later stages in the proceedings.

A ConocoPhillips spokesperson said the decision will allow the company to begin construction activities “immediately,” and said the project will provide “meaningful opportunities” for the state, its Alaska Native communities and for domestic U.S. energy production.

Bridget Psarianos, an attorney challenging the approval, called the planned construction schedule “aggressive” and said the judge’s decision is “heartbreaking.”

“We will do everything we can to protect the region while the merits of our case get heard,” Psarianos said in a statement.

The U.S. Interior Department declined to comment.

The Biden administration approved the project on March 13, drawing cheers from Alaska officials and the oil industry but criticism from environmental advocates who said the development undermines President Joe Biden’s highly publicized efforts to fight climate change and shift to cleaner sources of energy.

The approvals for the project in northern Alaska give ConocoPhillips permission to construct three drill pads, 25.8 miles of gravel roads, an air strip and hundreds of miles of ice roads. The 30-year project would produce up to 180,000 barrels of oil per day at its peak, according to the company.

In two lawsuits filed within days of the approval, environmental groups and Alaska Native groups said the government did not adequately consider less damaging alternatives and had wrongly assumed it did not have the power to stop ConocoPhillips from developing oil and gas resources on leases it owns.

ConocoPhillips has held the leases in the National Petroleum Reserve-Alaska since 1999. Former President Donald Trump’s administration first approved the project in 2020. But Gleason blocked it a year later, finding its environmental impact analysis was flawed.

The cases are Sovereign Inupiat for Living Arctic v. Bureau of Land Management and Center for Biological Diversity v. Bureau of Land Management, U.S. District Court for the District of Alaska, Nos. 3:23-cv-00058 and 3:23-cv-00061.


This article has been fact-checked by Arctic Today and Polar Research and Policy Initiative, with the support of the EMIF managed by the Calouste Gulbenkian Foundation.

Disclaimer: The sole responsibility for any content supported by the European Media and Information Fund lies with the author(s) and it may not necessarily reflect the positions of the EMIF and the Fund Partners, the Calouste Gulbenkian Foundation and the European University Institute.