🇮🇸 Iceland’s first wind farm commences operations

Ásbjörg Kristinsdóttir, Executive Vice President of Construction, and Daði Már Kristófersson, Minister of Finance and Economic Affairs, connected to Landsvirkjun's Control Centre to start up the wind turbines.

September 15, 2026

Iceland’s first wind farm, Vaðalda Wind Farm, was commissioned at a special ceremony on 15 September.

Formal ceremony in Vaðalda Wind Farm

Iceland’s first wind farm, Vaðalda Wind Farm, was commissioned at a special ceremony on 15 September. Landsvirkjun employees, contractors, members of the local community and other guests celebrated as Daði Már Kristófersson, Minister of Finance and Economic Affairs, declared outside Landsvirkjun’s new control centre that the wind farm was ready for operation. The blades began to turn and electricity started flowing into Landsnet’s transmission system.

Ásbjörg Kristinsdóttir, Executive Vice President of Planning and Construction, welcomed guests. Addresses were also given by Brynja Baldursdóttir, Chairman of the Board of Landsvirkjun; Hörður Arnarson, CEO; Jóhann Páll Jóhannsson, Minister for Energy, the Environment and Climate; and Sigurgeir Björn Geirsson, Senior Project Manager for Vaðalda Wind Farm. The Minister of Finance and Economic Affairs then took the stage and established radio contact with Landsvirkjun’s new control centre.

Fourteen wind turbines

Fourteen wind turbines have now been erected at Vaðalda Wind Farm, with a further 14 to be installed next year. The entire wind farm is expected to be fully operational by the end of 2027.

Vaðalda Wind Farm is located in Landsvirkjun’s largest generation area, the Þjórsá and Tungnaá area. Landsvirkjun, the national power company of Iceland, operates seven hydropower stations in the area, with an eighth to be added when Hvammur Hydropower Station comes online. Construction of Hvammur is already under way.

Vaðalda Wind Farm is situated on a lava and sand plain east of the Þjórsá River, south of Sultartangi Dam. Wind power is particularly well suited to operating alongside hydropower. Iceland’s winds are strongest during the winter, when inflow into hydropower reservoirs is at its lowest. This allows us to conserve water in what could be described as our large batteries. In summer, when winds tend to be lighter, reservoir levels are better able to support electricity generation.

    First wind farm to pass through the Master Plan process

    Vaðalda Wind Farm is the first wind farm to go through the Icelandic Government’s Master Plan for Nature Protection and Energy Utilisation. Its location is particularly favourable because much of the necessary infrastructure is already in place, including transmission lines, roads and other structures.

    Even so, construction of the wind farm has involved extensive works. The foundation of each wind turbine required around 70 tonnes of steel and more than 400 cubic metres of concrete. The foundations for the 14 turbines erected so far therefore contain approximately 980 tonnes of steel and 5,600 cubic metres of concrete. A concrete batching plant was set up on site, as otherwise close to 700 conventional concrete-truck loads would have been required.

    Each wind turbine weighs approximately 582 tonnes. With a blade at its highest point, a turbine stands around 150 metres tall. Cables running between the turbines and the substation have a combined length of 80 kilometres. Within the construction area itself, 20 kilometres of roads had to be built and 20 kilometres of trenches excavated.

    Major transport operation

    Construction of the wind farm required an extensive transport operation when the turbine components were shipped to Iceland. The first load was transported in early May and the final one in late July. Transport took place on an average of six nights each week.

    Roads along the approximately 130-kilometre route from the port of Þorlákshöfn to Vaðalda Wind Farm were reinforced, road bends were modified, streetlights and traffic signs were temporarily removed, and traffic had to be carefully managed to ensure that everyone could travel safely.

    New Landsnet substation at Ferjufit

    To connect Vaðalda Wind Farm to the transmission system, Landsnet has commissioned a new 220 kV substation at Ferjufit. The substation is housed indoors, providing equipment with better protection from weather and other environmental conditions. Its design also allows for possible future expansion.

    The substation is connected to the Sigalda 3 transmission line, which is now known as Ferjufit 1 west of the substation. Part of the overhead line had to be relocated as part of the project. Eleven new transmission towers and three terminal structures were erected, while nine older towers on the Sigalda 3 line were removed.

    More information

    Landsvirkjun
    Katrínartún 2, 105 Reykjavík, Iceland
    [email protected]
    +354 515 9000
    For more information, visit Landsvirkjun.


    Originally published on September 15, 2026 by Landsvirkjun.

    Announcements are published as a service to readers. The sender is responsible for all content.
    Announcements for publication can be submitted to [email protected]

    Country

    iceland

    Enjoy reading Arctic Today?

    At Arctic Today, we strive every day to bring you reliable information on one of the world’s most dynamic and rapidly changing regions. Independent journalism ensures that stories about Far North communities, businesses, and governments are told without fear or favor. Your support helps us continue our important mission. Become a supporter today and join us in getting the word out on this vital region. Together, we can ensure that the Arctic story is told accurately and responsibly. Arctic Today is a U.S. non-profit organization. Donate to support Arctic Today here.